Planning guide

How long a Brevard kitchen remodel takes

A kitchen schedule is a chain of dependent steps, and the weakest link is usually not demolition. It is cabinet delivery, permit review or a failed inspection. This guide lists the stages in order and shows what to ask for in writing so a delay can be traced to one step.

Get My Free Estimate

Free estimate, no obligation. Takes about a minute.

Stage one: planning and selections

Before anything is ordered, the contractor measures, you choose cabinets, counters, appliances and fixtures, and the scope is written down. Changes made after this point cost time as well as money. Appliance models matter now, since cutouts and utilities depend on them.

Stage two: permit and ordering

If a permit is needed, the contractor applies through your city or Brevard County, and review takes time. Cabinets are ordered, often at the same time. Ask for the application date and the order date in writing, and ask who tracks reviewer comments.

Stage three: demolition and rough-in

If an inspection fails, work stops until it is corrected and re-inspected.

  • Old cabinets, counters and sometimes flooring are removed.
  • Walls are opened or closed as the plan requires.
  • Plumbing and electrical rough-in is done by licensed trades.
  • A rough-in inspection happens before walls are closed.

Stage four: cabinets and counters

Cabinets arrive and are checked against the order, then installed. Counters are templated after the cabinets are set, then fabricated and installed. This gap, between templating and counter installation, is often the longest quiet period in a project.

Stage five: finish work and final inspection

Backsplash, plumbing and electrical connections, appliances, paint and trim complete the room. A final inspection closes the permit. Then you walk through the kitchen with the contractor and list anything to correct.

What to ask for in writing

Ask for a schedule that separates permit approval, cabinet delivery, each inspection, templating, counter installation and the final walkthrough. Ask who tells you when a date slips and what the contractor does about it. Keep each version of the schedule.

Planning for life without a kitchen

Set up a temporary kitchen in another room with a microwave, a small refrigerator and a table. Ask the contractor when the water will be off and when the dishwasher can be used again. Plan for dust, and ask how the work area will be sealed from the rest of the house.

Keeping the schedule honest

Weather can also matter in Brevard, since summer storms may interrupt exterior deliveries and disposal pickups. Ask how the contractor plans for it.

Ask the contractor to update the schedule each time a date moves, with the reason. A running record helps you plan, and it shows whether delays come from permits, materials or inspections.

Ask also what the contractor does to keep the crew working while a delivery or an inspection is pending, since idle days stretch the project.

Reading a kitchen estimate

A kitchen bid for your project should name the cabinet line, countertop material, appliances allowance, plumbing and electrical work and permits as their own items. Kitchen estimates, explained. Ask when cabinets would be ordered, how long delivery takes and what happens to your kitchen use in between. A bid that names a start date without mentioning lead times for cabinets and countertops may leave a gap you discover later. Ask also which appliances are included, who handles disposal of the old kitchen and whether the price changes if the electrician finds an undersized panel or circuit.

From layout idea to finished kitchen

  1. Measure the room and agree on the layout, including appliances and storage.
  2. Compare itemized proposals covering cabinets, counters, plumbing and electrical.
  3. Order cabinets and counters early because lead times drive the calendar.
  4. Confirm permits, inspections and who coordinates the trades.
  5. Walk the finished kitchen, test appliances and keep warranty and permit papers.

Before you pick a kitchen contractor

Confirm the license on the DBPR site and ask for proof of liability insurance before you commit to this kind of project. Ask which licensed electrician and plumber will do that work, and whether any wall coming out is load-bearing. More on the process is on how to check a contractor. Ask who coordinates the plumber, electrician and countertop fabricator, and whether the permit covers the trades together. Good answers are specific names and steps, not general reassurance. Also ask what the warranty covers, who answers a callback after the final walkthrough, and how a damaged cabinet or counter is handled before it goes in.

Kitchen remodeling questions

How long does a kitchen remodel take?

It depends on scope, permit review, cabinet lead time, inspections and counters. Ask each bidder for a written schedule that separates these steps, so a delay can be traced to a specific stage. Ask the contractor to update that schedule whenever a delivery date changes.

What usually causes delays?

Cabinet delivery, permit review, failed inspections and changes to selections after ordering. Ask the contractor how each is managed and who tells you when a date moves. Confirming measurements on site before cabinets are ordered helps, and so does choosing finishes before the order is placed.

When are countertops installed?

After cabinets are installed and templated, which means a gap while the counters are fabricated. Ask the fabricator for lead time and the contractor how they will keep other work moving during the wait. Schedule the template visit as soon as the cabinets are level and secured.

Can I use my kitchen during the remodel?

Only partly. Demolition and installation make the room unusable, so plan a temporary setup. Ask the contractor how many days you will be without water and power in the kitchen. A temporary sink in the laundry room or garage, a microwave and a small table cover most households through the gap.

Kitchen projects behind this guide

Where this page gets its permit facts:Florida Statutes 553.79 (permits and exemptions) (accessed Nov 2026); Florida Statutes 489.113 (contractor scope and subcontracting) (accessed Nov 2026). General information, not legal advice; confirm with the office that covers your address.

Reviewed November 2026.